General checklist for any loan that has been:
- Created
- Approved
- Denied/Withdrawn
- Closed & Funded
2026 Loan File Checklist for ARIVE.pdf
- Data Integrity- Complete all loan information in ARIVE
- Loan Program/Rate/Loan Details should match final CD/Investor/correct loan channel
- Borrower’s Credit Authorization - whether generated in ARIVE or Lender portal; a copy should be in ARIVE
- Borrower’s eConsent – if generated in ARIVE this will auto populate and be housed with documents
- Credit Report – whether generated in ARIVE or Lender portal; a copy MUST be in ARIVE
- Borrower’s Certification and Authorization - if generated in ARIVE this will auto populate and be housed with documents; otherwise upload from Lender’s portal
- AUS (if applicable) - whether generated in ARIVE or Lender portal; a copy should be in ARIVE
- Preapproval (if applicable) - whether generated in ARIVE or Lender portal; a copy should be in ARIVE
- Borrower Documents – all docs sent to investor for approval (ID/income/asset/lease/etc.) If it went to investor, it should be in ARIVE
- Initial Disclosures- obtain/retrieve signed disclosures from lender portal and upload into ARIVE
- REMINDER: Once loan becomes TRID, initial disclosures MUST be sent within three (3) days; exceptions may apply based on loan products (i.e., DSCR, Reverse, etc.)
- Intent to Proceed (ITP) – signed disclosure; we MUST have evidence in ARIVE file
- Property Documents – (if applicable) Contract/addendums/appraisal/final/survey
- HOI (homeowners’ insurance) - Current policy(s) with correct mortgagee clause
- Title Documents – upload applicable docs ((CPL/Title/Prelim CD/wiring instructions)
- Loan Decision Documents – upload applicable docs from Lender’s portal (suspense/approval/final)
- Final Lock Confirmation
- Funded Loan – to avoid delaying your pay
- Complete Signed Closed Loan Package
- Milestones moved to Funded milestone
- Lender Disbursement Check or Lender wire breakdown
- Be sure to provide title/closing agent with C2C wiring instructions
- Pipeline Management
- All users are responsible for updating and managing their pipeline
- Adverse Action milestone to be completed in ARIVE for denied, withdrawn and/or cancelled loans
- Copy of Adverse Action Notice from Lender must be uploaded
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article